Answer: 1 week Explanation: For a standard residential lot, we typically have a one-week turnaround. However, if you need results sooner, we can often accommodate faster timelines for an additional rush fee. Let us know your timeline, and we’ll work to meet your needs efficiently. |
Alliance Land Surveyors |
Answer: 1 week Explanation: Just walk around find look at map and find metal bR in ground |
J&T 6 |
Answer: 4 weeks Explanation: Again it depends on the project some are quick (small projects) and some take a bit of time. It also depends on the back log of scheduling. |
Daniel H. Elder, Land Surveyor |
|
ProMatcher |
Answer: 2 weeks Explanation: Typically a boundary/lot survey will take anywhere from 2 to 4 days to complete and have recorded depending on the site conditions. We ask for a minimum 2 week window to complete the work so that we have adequate time for scheduling. |
Apex Land Surveys |
Answer: 2 weeks Explanation: There are many variables in land surveying with laws that change what each project may require. It is best to allow at least 2 weeks for total completion of small standard residential surveys. |
Skinner Land Survey Co., Inc. |
Answer: 1 week Explanation: Depending primarily on the weather conditions.
Work load can increase lead time. Call to check availability. |
Tim Phipps, Surveyor |
|
ProMatcher |
Answer: 1 week Explanation: Of course it is hard to do field work in the rain. We will strive to get your work done professionally and quickly. |
Land & Lake Surveying |
Answer: 1 week Explanation: We try to keep up with residential lot surveys as fast as they come in, as it is all to easy to fall behind. Large jobs that can take weeks can afford a few half days off while we help someone with a smaller piece of property. |
Accurate Surveying PLLC |
Answer: 1 week Explanation: Less than one week is a better estimate |
California Engineering & Surveying Inc |
|
ProMatcher |
Answer: 2 weeks Explanation: Timing depends upon inclement weather & work load. |
ACRE Engineers & Land Surveyors |
Answer: 1 week Explanation: one week is a good time unless access is difficult |
Construction Management Group |
Answer: 1 week Explanation: Weather impacts a surveyor's schedule. Also, certain times of the year are busier than others |
B. Terrell Meunier, Land Surveyor |